CNC machined fuel filling lids for JFD

Fuel filling lids machined to JFD's own file, with a sample tested by their team before we made the batch.

Client
JFD
What it is
The top lid of a fuel filling funnel
Cut into each lid
A threaded centre bore, two side ports and four bolt holes
Made in
Black POM-C, left as machined
A sample lid for JFD to test, then six production lids
1 + 6
How much smaller than its tube the O-ring lip is cut, confirmed with JFD
0.10 to 0.13 mm

What we brought

  1. What we can do

    Made to your file, as drawn

    We machined the lid from JFD's STEP file and drawing as supplied, with no design changes, in black POM-C.

  2. How we look after you

    A sample to test before the batch

    JFD's team tested one lid on their side and judged it serviceable before we machined the other six.

  3. What you get

    Checked before it left us

    We confirmed the O-ring lip tolerance with JFD, test-fitted the side ports and held the batch for a fitting check.

The build

How we built it

5 steps, from the brief to the finished piece. Pick a step to jump to it.

The brief

Step 1 of 5 · 22/07/2026

Quantity
One sample, then six production lids
Material
Black POM-C
Finish
As machined
Scope
Machining only, with no design changes

At Additive Inn, our 3D printing studio in Singapore, we machine parts to our clients' own files. JFD needed seven fuel filling lids made in black POM-C to their STEP file and drawing, with one sample to test before the rest.

Drawing check and sample

Step 2 of 5 · 04/08/2026

We read JFD's drawing for machining, then cut one sample lid. We photographed and measured its holes for JFD's engineer, who collected it on 06/08/2026 and tested it with his team. On 13/08/2026 they judged it serviceable.

The sample lid, ready for JFD.
The thread through the centre bore.
The sample's underside and rim notches.
Measuring the sample's holes for JFD.
DrawingOur drawing of the lid.
RenderA design note on the bore.
DrawingThe tube fit, marked on the section.

Production

Step 3 of 5 · 24/08/2026

We machined the six production lids to the approved sample, watching the thread alignment JFD asked us to check. Before we cut the batch, we confirmed with JFD that the lip for the O-ring is 0.10 to 0.13 mm smaller than its tube.

Lids halfway through the batch.
Six lids, machined.
The bore and ports, close.
The batch from above.
One lid, collar up.
The rim notches.
The full set.
From the side.
Stacked up.

Checks and fitting

Step 4 of 5 · 01/09/2026

With the batch done, we tried a fitting in the two side ports, and it went in. We held the lids until JFD's engineer came to our studio on 18/09/2026 for a fitting check.

The six production lids, ready for checks.

The final build

Step 5 of 5 · 22/09/2026

We delivered the six lids to JFD's team on 22/09/2026. Each is black POM-C, left as machined, with a threaded centre bore, two side ports, four bolt holes in the flange and a groove around the raised collar.

The collar, groove and side ports.